Graphic of overall project schedule. Comp Plan Amendment lasts from Q1 through Q3 of 2022. Code Amendment lasts from Q3 2022 through Q2 of 2023. Master Plan / Development Agreement lasts from Q2 of 2023 through Q4 of 2024. Site Plan Approval / Permitting lasts from Q4 of 2024 through Q3 of 2025. Construction lasts from Q2 of 2025 through Q2 of 2027